AustinThe grid operator says 474 gigawatts of requests sit in the queue, five times peak demand.
Governor Abbott froze new grid connections less than a year after courting AI data centers, since the grid operator can’t tell real demand from speculative filing.
Regulators must now audit every project’s power draw before Batch Zero can proceed.
Sources: Ars Technica