UlanqabChina’s Envision says wind farms feed 80% of its data centre.
Substations take 12-18 months to build, and data-centre customers want capacity in 6.
Envision says dedicated lines carry the wind power, with batteries, forecasting models and 800-volt direct current cutting conversion steps.
Envision’s account does not say how the site runs when the wind drops.
Envision plans 5 gigawatts of desert sites by 2030 under Mission Gobi.